Indonesia Mining Environmental Permit: When an AMDAL or UKL-UPL Applies and How It Attaches to the IUP

By Teramine EditorialPublished 19 November 202610 min readCompany: Kementerian Lingkungan Hidup

Every Indonesian mine sits on an environmental approval. Under PP 22/2021 the Persetujuan Lingkungan — issued on an AMDAL or a UKL-UPL — is a precondition of the business licence, and PP 96/2021 makes it a condition for moving an IUP or IUPK into production. This explainer sets out the scale thresholds that decide which document applies, who issues the approval since October 2025, what the approval binds the holder to, and when it must be redone.

Before an Indonesian mining licence can move from exploration into production, the holder has to show an environmental approval. That approval — the Persetujuan Lingkungan — is not a side permit. Under the government's environmental regulation it is a precondition of the business licence itself, and it fixes the environmental obligations the mine will be measured against for as long as it operates.

For a foreign investor, that makes the environmental document one of the first things to check in a target. This explainer covers the Indonesia mining environmental permit: when a mine needs a full AMDAL and when a UKL-UPL is enough, how the approval attaches to the IUP or IUPK, who issues it, what it obliges the holder to do, and what forces it to be reopened. Every rule below comes from the regulations listed at the end, which we read in full text.

The instruments

InstrumentDateIts role
Government Regulation (PP) No. 22 of 2021 on Environmental Protection and Management2 February 2021defines AMDAL, UKL-UPL, SPPL and the Persetujuan Lingkungan; sets the screening, drafting, public-involvement and change rules; revoked the 2012 environmental-permit regulation (PP 27/2012)
Minister of Environment and Forestry Regulation (Permen LHK) No. 4 of 20211 April 2021the list of activities that need an AMDAL, a UKL-UPL or an SPPL, with the mining thresholds
PP No. 96 of 2021 on mineral and coal mining business activities9 September 2021makes the environmental document and approval a requirement for the IUP/IUPK production stage
Minister of Environment Regulation (Permen LH/BPLH) No. 22 of 2025 on authority to issue environmental approvalsissued 22 October 2025decides which level of government issues the approval for which mining activity

Three documents, one approval

PP 22/2021 says every planned business or activity with an environmental impact must have one of three documents:

  • AMDAL — a study of the *significant* impacts of a planned activity, used as a precondition for the decision on whether it may go ahead and written into the business licence. It is made up of the Andal (the impact analysis) and the RKL-RPL (the environmental management and monitoring plans).
  • UKL-UPL — environmental management and monitoring set out in a standard form, for activities that do *not* have significant impacts.
  • SPPL — a statement of undertaking to manage and monitor the environment, for activities outside both lists.

The approval that results is the Persetujuan Lingkungan. For an AMDAL activity it takes the form of a Keputusan Kelayakan Lingkungan Hidup (SKKLH) — a decision that the plan is environmentally feasible. For a UKL-UPL activity it is an approved Pernyataan Kesanggupan Pengelolaan Lingkungan Hidup (PKPLH).

PP 22/2021 sets four rules on the approval that matter to an investor:

  1. it is required for every activity with a significant or non-significant impact;
  2. it is a precondition for issuing the business licence (Perizinan Berusaha);
  3. it ends when the business licence ends; if the licence is extended without a change to the activity, the existing approval may be used as the basis for the extension;
  4. its ending is evidenced by the holder having carried out environmental management in the post-operation stage.

When a mine needs an AMDAL

Permen LHK 4/2021 sets the thresholds. Exploration is treated separately from production.

Exploration of coal, metal minerals, non-metal minerals and rock needs a UKL-UPL at every scale (classed as medium-low risk).

Operation-production is where the AMDAL thresholds apply:

Production-stage activityAMDAL at or aboveBelow this: UKL-UPL
Coal miningpermit area ≥ 200 ha; area opened for mining ≥ 50 ha (cumulative per year); production capacity ≥ 1,000,000 t/yr; overburden moved ≥ 4,000,000 bcm/yr; hazardous (B3) waste backfilled into the mined-out area (any scale)permit area < 200 ha; opened area < 50 ha/yr; capacity < 1,000,000 t/yr; overburden < 4,000,000 bcm/yr
Metal minerals (energy and metal sectors)permit area ≥ 200 ha; opened area ≥ 50 ha/yr; ore production ≥ 300,000 t/yr; overburden ≥ 1,000,000 bcm/yr; B3 waste backfilling (any scale); B3 waste placed in a tailings dam (any scale)permit area < 200 ha; opened area < 50 ha/yr; ore < 300,000 t/yr; overburden < 1,000,000 bcm/yr
Non-metal minerals or rockpermit area ≥ 200 ha; opened area ≥ 50 ha/yr; capacity ≥ 500,000 t/yr; overburden ≥ 1,000,000 bcm/yrpermit area 5–200 ha; smaller areas, capacities and overburden volumes fall into lower UKL-UPL classes
Processing and refining integrated with miningmetal minerals: all scales; non-metal minerals and rock ≥ 500,000 m³/yrnon-metal minerals and rock 50,000–500,000 m³/yr

The list classes metal-mineral mining as AMDAL category A and non-metal/rock mining and integrated processing as category C. The scientific reasons it gives for the mining thresholds include air quality, noise, vibration, erosion and sedimentation, river water quality, groundwater, flooding, acid mine drainage, local traffic, and disturbance to flora, fauna and aquatic life.

Location can trigger an AMDAL on its own. Both PP 22/2021 and Permen LHK 4/2021 require an AMDAL for an activity located inside or directly bordering a protected area (*kawasan lindung*) — where the project-site boundary touches the protected area's boundary, or where scientific consideration shows it could affect that area's function — regardless of scale.

How the approval attaches to the IUP

PP 96/2021 ties the environmental track to each licence stage:

Licence stepEnvironmental requirement in PP 96/2021
Granting an IUP (exploration)a signed statement of undertaking to comply with environmental protection laws
Upgrading an IUP or IUPK to operation-productionthe environmental document and Persetujuan Lingkungan issued by the authorised agency, plus the reclamation plan and post-mining plan; the technical requirements include a feasibility study approved by the minister
Transferring an IUP (with ministerial approval)a report on reclamation carried out and proof that the reclamation guarantee has been placed; the transferee signs an undertaking to comply with environmental law
Extending the production periodamong other items, a report on environmental management and reclamation

The regulation's own definition of a feasibility study includes the analysis of environmental impact, and the production upgrade needs both a ministry-approved feasibility study and the environmental approval. In other words, the environmental work belongs to the end of exploration, not to the first year of production.

Who issues it — the 2025 authority rule

Permen LH/BPLH 22/2025 assigns authority by location: the Minister for cross-provincial projects, national strategic projects and certain listed activities; the governor for cross-district projects within one province; the regent or mayor for projects in a single district. Issuance is carried out by the OSS licensing institution (or, for regional authority, the provincial or district investment office), through the environment ministry's information system integrated with OSS.

For mining, the regulation's annexes are specific:

  • Minister (Annex I): production-stage coal mining at AMDAL scale; production-stage metal-mineral mining at AMDAL scale; production with submarine tailings placement; coal or metal-mineral production followed by processing and refining of metal minerals; and coal or metal-mineral mining that involves B3 waste backfilling, a tailings dam, fly-ash/bottom-ash backfilling, an integrated special terminal, or integrated processing.
  • Governor (Annex II): production-stage non-metal minerals and rock; and production-stage coal and metal-mineral mining at UKL-UPL scale.

The regulation also says applications already declared administratively complete when it came into force continue to issuance under the old route.

How long the process takes on paper

PP 22/2021 sets these formal steps and time limits for an AMDAL:

  • Screening. The proponent screens itself; if it cannot, it asks the environmental agency to decide which document applies and which authority assesses it.
  • Spatial-plan check first. An AMDAL is prepared at the planning stage, and the site must conform to the spatial plan. If it does not, the AMDAL cannot be assessed and is returned.
  • Public involvement. Directly affected communities are involved through an announcement and a public consultation before the terms of reference are drafted; they have 10 working days from the announcement to submit written comments.
  • Drafting time. The Andal and RKL-RPL must be drafted within 180 days (category A), 120 days (category B) or 60 days (category C); very complex studies can take longer on request.
  • Decision. After the feasibility-test team's recommendation, the minister, governor or regent must issue the SKKLH — or a decision of environmental *in*feasibility — within 10 working days.
  • The team. The AMDAL is drafted by a team appointed by the proponent; its chair must hold a competency certificate.

For a UKL-UPL, the approval is issued through the information system within 2 working days if the form needs no revision.

What the approval binds the holder to

The SKKLH is not a pass/fail stamp. PP 22/2021 requires it to set out the holder's obligations, including to:

  • comply with its own RKL-RPL — the management and monitoring plan written into its AMDAL;
  • meet the obligations in its Persetujuan Teknis (technical approvals covering effluent and emission standards, hazardous-waste management and/or traffic impact);
  • prepare a guarantee fund for restoring environmental functions;
  • report on the environmental conditions of its licence every six months;
  • apply to change the approval before changing the activity;
  • carry out an environmental audit in the post-operation stage.

The decision stays valid for as long as the activity runs without change. This is why two mines of similar size can carry different environmental duties: each is assessed against the commitments in its own approved document, alongside the general standards that apply to everyone.

When the approval has to be reopened

PP 22/2021 lists the changes that require the Persetujuan Lingkungan to be amended. Some require a new environmental document:

  • a change in technical specification, equipment, raw materials or facilities that affects the environment;
  • an increase in production capacity;
  • an expansion of the land area;
  • a change in operating period or duration;
  • a fundamental environmental change from a natural event or other cause;
  • the plan not being carried out within three years of the approval.

Others are amended without a new document — among them a change in the identity of the responsible party, a change of administrative region, and a reduction in area. Where a change pushes the activity's cumulative scale into AMDAL territory, a new AMDAL is required. Otherwise the route is a new UKL-UPL or an addendum to the Andal and RKL-RPL, of type A, B or C.

Catatan Teramine

*This section is Teramine's editorial analysis, not a statement of fact and not legal advice.*

Read the approval against the mine plan. The thresholds are in tonnes, hectares and bank cubic metres. A target whose approved document was sized for a smaller operation than the one in its pitch — more ore per year, a bigger opened area, a new tailings dam, an integrated smelter — faces an amendment, and possibly a new AMDAL, before it can lawfully produce at the pitched rate. We read each line in the Permen LHK 4/2021 table as a separate trigger; confirm the reading with a formal screening.

A UKL-UPL on a metal mine is a question, not a red flag. It can be correct for a small permit area. But check the numbers behind it: a metal-mineral operation crossing any of the listed scales, or adding a tailings dam or integrated processing, sits in the AMDAL column.

The three-year clock. An approval for a plan not carried out within three years needs a new document. A dormant licence holding an old AMDAL may not be as "permitted" as it looks.

Ask for the trail, not the certificate. The six-monthly reports, the RKL-RPL and the technical approvals show whether the holder is living up to its approval. A vendor that can produce the SKKLH but not the reports is showing half the file.

Who signed it matters. Since October 2025 the issuing level depends on location and activity. For coal or metal mining at AMDAL scale, an approval on the current rule comes from the Minister; one issued earlier by another level is not wrong on that ground alone, but note which rule it was issued under.

For document preparation and approvals on a specific licence, see Teramine's [permit services](/en/layanan-izin). For the licence types the approval attaches to, see [IUP vs IUPK](/en/news/iup-vs-iupk); for the operating duties that follow, see [tailings management](/en/news/indonesia-mine-tailings-management), [mine water management](/en/news/indonesia-mine-water-management), [mining in forest areas](/en/news/indonesia-mining-in-forest-areas) and [mine closure](/en/news/mine-closure-in-indonesia); for the transaction itself, [how to buy a mine in Indonesia](/en/news/how-to-buy-a-mine-in-indonesia). Listed projects are on the [marketplace](/en/marketplace).

What we could not confirm

  • Whether Permen LHK 4/2021 has been amended or replaced. The BPK legal database lists it as in force; we did not find a replacement, but did not exhaustively check.
  • The AMDAL category for coal mining. The category cell in the coal row of Permen LHK 4/2021 did not extract legibly; we give categories only for metal minerals (A) and non-metal/rock and integrated processing (C).
  • PP 28/2025 on risk-based licensing, which Permen LH/BPLH 22/2025 cites as its basis. We did not read it, so this article does not describe how it changed the OSS process.
  • Whether PP 22/2021's time limits have been amended since 2021. The figures above are from the 2021 text.
  • Actual processing times. The deadlines are regulatory maxima for each step; we have no official data on how long approvals take in practice.

Sources

  • PP No. 22 of 2021 on Environmental Protection and Management (2 February 2021) — official text via JDIH BPK.
  • Permen LHK No. 4 of 2021 — list of activities requiring AMDAL, UKL-UPL or SPPL (1 April 2021), JDIH BPK.
  • PP No. 96 of 2021 on mineral and coal mining business activities (9 September 2021), JDIH BPK.
  • Permen LH/BPLH No. 22 of 2025 on authority to issue environmental approvals (22 October 2025) — text and JDIH BPK metadata.

Sources & References

According to an official statement from Peraturan Pemerintah No. 22 Tahun 2021 tentang Penyelenggaraan Perlindungan dan Pengelolaan Lingkungan Hidup (2 February 2021) — official copy via JDIH BPK (Salinan PP Nomor 22 Tahun 2021.pdf). Read for: definitions (Persetujuan Lingkungan, Amdal, UKL-UPL, SKKLH, PKPLH, SPPL, Andal, RKL-RPL); Art. 3 (approval required for significant and non-significant impacts, precondition of business licence, ends with the licence, extension on existing approval, post-operation evidence); Arts. 4–5 (Amdal/UKL-UPL/SPPL; Amdal by scale or in/adjacent to protected areas); Art. 20 (screening); Art. 21 (spatial-plan conformity, otherwise returned); Art. 28 (community involvement, 10 working days); Arts. 41–42 (categories A/B/C; 180/120/60 days); Art. 49 (SKKLH within 10 working days; contents and obligations incl. RKL-RPL, Persetujuan Teknis, guarantee fund, six-monthly reporting, change application, post-operation audit; validity); Art. 62 (UKL-UPL approval within 2 working days); Amdal team chair competency certificate; Arts. 89–91 (changes requiring amendment, new document vs. none, addendum types A/B/C). BPK metadata: status in force; revokes PP 27/2012., …

  1. 1
  2. 2
  3. 3
  4. 4

This article was rewritten with added context and data. Original sources are listed for transparency.

AMDALUKL-UPLEnvironmental PermitPersetujuan LingkunganPP 22/2021Permen LHK 4/2021PP 96/2021Due DiligenceIndonesia Mining Regulation
Share

Related Mining Opportunities

Mining projects currently offered on Teramine for this commodity.

Browse Mining Opportunities

Looking for mining investment opportunities in Indonesia?

Browse IUP projects available for take over, joint operation and joint venture on Teramine.

Explore Mining Opportunities

Own a mining asset or project?

Publish your mining opportunity to Teramine's investor network.

Submit Mining Opportunity

Ada Pertanyaan?

Konsultasi gratis dengan tim ahli kami

Hubungi Kami

Related Articles

Mine Closure in Indonesia: the Reclamation Obligation, the Guarantee, and What It Costs
Mining EnvironmentExplainer

Mine Closure in Indonesia: the Reclamation Obligation, the Guarantee, and What It Costs

Indonesia does not treat closure as a decision taken at the end of a mine's life. Reclamation is defined as running through every stage of the permit, the state holds a cash guarantee sized per hectare and per province, and nothing is released until the post-mining test is met at 100 per cent. Here is how the regime is built, and what it costs in 2026.

29 Sep 20268 min read
Indonesia Mining Water Management: The Drainage, Settling-Pond and Acid-Drainage Duties on an IUP Holder
Mining EnvironmentExplainer

Indonesia Mining Water Management: The Drainage, Settling-Pond and Acid-Drainage Duties on an IUP Holder

At an Indonesian mine, water is not an engineering afterthought — it is a set of named duties under the good-mining-practice rulebook. A holder must first study the hydrology, hydrogeology and rock geochemistry, then design drainage channels, settling ponds and pumps to a fixed rainfall standard, and must know whether its waste rock will generate acid drainage before it can be allowed to treat it. This explainer sets out the exact water duties under Permen ESDM No. 26 of 2018 and Kepmen ESDM No. 1827 K/30/MEM/2018 — and why a breach of them is a licence risk before it is an environmental one.

8 Oct 202610 min read
Indonesia Mine Tailings Management: The Design, Water, Monitoring and Closure Duties on an IUP Holder
Mining EnvironmentExplainer

Indonesia Mine Tailings Management: The Design, Water, Monitoring and Closure Duties on an IUP Holder

A tailings storage facility in Indonesia is a regulated structure, not just an engineering one. The good-mining-practice rulebook requires it to be designed, built and operated so it cannot pollute surface or groundwater, carries a mandatory structural-failure mitigation plan and emergency-response system, sits behind a settling-pond and acid-drainage regime, must be monitored against a defined list of parameters, and must be reclaimed at closure. This explainer sets out the exact duties on an IUP or IUPK holder under Permen ESDM No. 26 of 2018 and Kepmen ESDM No. 1827 K/30/MEM/2018 — and why a breach of the environmental duty is itself a listed ground for suspension or revocation.

7 Oct 202611 min read